Question No33:
A company has been asked to quote for a job. The company aims to make a net profit of
30% on sales. The estimated cost for the job is as follows:
Direct materials 10 kg @ £10 per kg
Direct labour 20 hours @ £5 per hour
Variable production overheads are recovered at the rate of £2 per labour hour.
Fixed production overheads for the company are budgeted to be £100,000 each year and
are recovered on the basis of labour hours.
There are 10,000 budgeted labour hours each year. Other costs in relation to selling, distribution and administration are recovered at the rate of £50 per job.
The company quote for the job should be
A. £572
B. £637
C. £700
D. £833
Answer: C
Friday, 20 November 2015
Thursday, 12 November 2015
Cima C01 Exam Question No 32
Question No 32:
A company produces a single product that passes through two processes. The details for process 1 are as follows:
Materials input 20,000 kg at $2·50 per kg
Direct labour $15,000
Production overheads 150% of direct labour
Normal losses are 15% of input in process 1 and without further processing any losses can be sold as scrap for $1 per kg.
The output for the period was 18,500 kg from process 1. There was no work-in-progress at the beginning or end of the period.
What value (to the nearest $) will be credited to the process 1 account in respect of the normal loss?
A. Nil
B. $3,000
C. $4,070
D. $5,250
Answer: B
A company produces a single product that passes through two processes. The details for process 1 are as follows:
Materials input 20,000 kg at $2·50 per kg
Direct labour $15,000
Production overheads 150% of direct labour
Normal losses are 15% of input in process 1 and without further processing any losses can be sold as scrap for $1 per kg.
The output for the period was 18,500 kg from process 1. There was no work-in-progress at the beginning or end of the period.
What value (to the nearest $) will be credited to the process 1 account in respect of the normal loss?
A. Nil
B. $3,000
C. $4,070
D. $5,250
Answer: B
Thursday, 5 November 2015
Cima C01 Exam Question No 31
Question No 31:
In a standard cost bookkeeping system, when the actual material usage has been greater than the standard material usage, the double entry to record this is:
A. Debit the material usage variance account, Credit the raw material control account
B. Credit the material usage variance account, Debit the raw material control account
C. Debit the material usage variance account, Credit the work-in-progress account
D. Credit the material usage variance account, Debit the work-in-progress account
Answer: A
In a standard cost bookkeeping system, when the actual material usage has been greater than the standard material usage, the double entry to record this is:
A. Debit the material usage variance account, Credit the raw material control account
B. Credit the material usage variance account, Debit the raw material control account
C. Debit the material usage variance account, Credit the work-in-progress account
D. Credit the material usage variance account, Debit the work-in-progress account
Answer: A
Thursday, 29 October 2015
Cima C01 Exam Question No 30
Question No 30:
P operates a standard marginal costing system. The following budgeted and standard cost information is available:
Budgeted production and sales 10,000 units
Variable production overheads – 5 hours x $4 $ 20 per unit
Actual results for the period were as follows:
Production and sales 11,500 units
Variable production overheads – 52,000 hours $195,000
The variable production overhead expenditure variance is
A. $35,000 adverse
B. $13,000 adverse
C. $13,000 favourable
D. $35,000 favourable
Answer: C
P operates a standard marginal costing system. The following budgeted and standard cost information is available:
Budgeted production and sales 10,000 units
Variable production overheads – 5 hours x $4 $ 20 per unit
Actual results for the period were as follows:
Production and sales 11,500 units
Variable production overheads – 52,000 hours $195,000
The variable production overhead expenditure variance is
A. $35,000 adverse
B. $13,000 adverse
C. $13,000 favourable
D. $35,000 favourable
Answer: C
Tuesday, 20 October 2015
Cima C01 Exam Question No 29
Question No 29:
G repairs electronic calculators. The wages budget for the last period was based on a standard repair time of 24 minutes per calculator and a standard wage rate of $10.60 per hour.
Following the end of the budget period, it was reported that:
Number of repairs 31,000
Labour rate variance $3,100 (A)
Labour efficiency variance Nil
Based on the above information, the actual wage rate during the period was:
A. $10.35 per hour
B. $10.60 per hour
C. $10.85 per hour
D. $11.10 per hour
Answer: A
G repairs electronic calculators. The wages budget for the last period was based on a standard repair time of 24 minutes per calculator and a standard wage rate of $10.60 per hour.
Following the end of the budget period, it was reported that:
Number of repairs 31,000
Labour rate variance $3,100 (A)
Labour efficiency variance Nil
Based on the above information, the actual wage rate during the period was:
A. $10.35 per hour
B. $10.60 per hour
C. $10.85 per hour
D. $11.10 per hour
Answer: A
Thursday, 15 October 2015
Cima C01 Exam Question No 28
Question No 28:
Which ONE of the following factors could explain a favourable direct material usage variance?
A. More staff were recruited to inspect for quality, resulting in a higher rejection rate.
B. When estimating the standard product cost, usage of material had been set using ideal standards.
C. The company had reduced training of production workers as part of a cost reduction exercise.
D. The material price variance was adverse.
Answer: D
Which ONE of the following factors could explain a favourable direct material usage variance?
A. More staff were recruited to inspect for quality, resulting in a higher rejection rate.
B. When estimating the standard product cost, usage of material had been set using ideal standards.
C. The company had reduced training of production workers as part of a cost reduction exercise.
D. The material price variance was adverse.
Answer: D
Thursday, 8 October 2015
Cima C01 Exam Question No 27
Question No 27:
X operates a standard marginal costing system. The following budgeted and standard cost information is available:
A. $18,000 adverse
B. $3,000 adverse
C. $3,000 favourable
D. $18,000 favourable
Answer: D
X operates a standard marginal costing system. The following budgeted and standard cost information is available:
- Budgeted production and sales 10,000 units
- Direct material cost – 3 kg x $10 $30 per unit
- Production and sales 11,500 units
- Direct material – 36,000 kg $342,000
A. $18,000 adverse
B. $3,000 adverse
C. $3,000 favourable
D. $18,000 favourable
Answer: D
Subscribe to: