Question No33:
A company has been asked to quote for a job. The company aims to make a net profit of
30% on sales. The estimated cost for the job is as follows:
Direct materials 10 kg @ £10 per kg
Direct labour 20 hours @ £5 per hour
Variable production overheads are recovered at the rate of £2 per labour hour.
Fixed production overheads for the company are budgeted to be £100,000 each year and
are recovered on the basis of labour hours.
There are 10,000 budgeted labour hours each year. Other costs in relation to selling, distribution and administration are recovered at the rate of £50 per job.
The company quote for the job should be
A. £572
B. £637
C. £700
D. £833
Answer: C
Friday, 20 November 2015
Thursday, 12 November 2015
Cima C01 Exam Question No 32
Question No 32:
A company produces a single product that passes through two processes. The details for process 1 are as follows:
Materials input 20,000 kg at $2·50 per kg
Direct labour $15,000
Production overheads 150% of direct labour
Normal losses are 15% of input in process 1 and without further processing any losses can be sold as scrap for $1 per kg.
The output for the period was 18,500 kg from process 1. There was no work-in-progress at the beginning or end of the period.
What value (to the nearest $) will be credited to the process 1 account in respect of the normal loss?
A. Nil
B. $3,000
C. $4,070
D. $5,250
Answer: B
A company produces a single product that passes through two processes. The details for process 1 are as follows:
Materials input 20,000 kg at $2·50 per kg
Direct labour $15,000
Production overheads 150% of direct labour
Normal losses are 15% of input in process 1 and without further processing any losses can be sold as scrap for $1 per kg.
The output for the period was 18,500 kg from process 1. There was no work-in-progress at the beginning or end of the period.
What value (to the nearest $) will be credited to the process 1 account in respect of the normal loss?
A. Nil
B. $3,000
C. $4,070
D. $5,250
Answer: B
Thursday, 5 November 2015
Cima C01 Exam Question No 31
Question No 31:
In a standard cost bookkeeping system, when the actual material usage has been greater than the standard material usage, the double entry to record this is:
A. Debit the material usage variance account, Credit the raw material control account
B. Credit the material usage variance account, Debit the raw material control account
C. Debit the material usage variance account, Credit the work-in-progress account
D. Credit the material usage variance account, Debit the work-in-progress account
Answer: A
In a standard cost bookkeeping system, when the actual material usage has been greater than the standard material usage, the double entry to record this is:
A. Debit the material usage variance account, Credit the raw material control account
B. Credit the material usage variance account, Debit the raw material control account
C. Debit the material usage variance account, Credit the work-in-progress account
D. Credit the material usage variance account, Debit the work-in-progress account
Answer: A
Subscribe to:
Posts (Atom)